| Date | Time | District Affected | Sector / Areas | Reason | Status |
|---|---|---|---|---|---|
| 24th January 2020 | 12:00 PM - 01:30 PM | Gasabo & Nyarugenge | Gatsata in Gasabo & Muhima (Nyabugogo Cell) in Nyarugenge | Extension works on Kigali feeder from Jabana Substation | Past |
| 25th January 2020 | 09:00 AM - 12:00 PM | Rubavu | Cyanzarwe & Nyakiriba | Upgrading works on Gisenyi feeder at Singaye T-Off | Past |
| 23rd January 2020 | 12:00 PM - 01:30 PM | Gasabo | Kinyinya (Batsinda Center) | Maintenance works on « Deutsche-Welle» feeder at Batsinda T-Off | Past |
| 24th January 2020 | 12:00 PM - 02:00 PM | Burera | Rugengabare, Gitovu, Cyeru, Rusarabuye, Rwerere and Butaro and RUGEZI Power Plant | Maintenance and extension works on Kirambo Feeder | Past |