Overview
This may be done either through solicited or non- solicited option/proposal.
The company must have expressed its interest and fill the appropriate due diligences with RDB.

- REG/EUCL/EDCL tendering process is based on competitive bidding process
- PPP law was set in place in 2016
- Annual procurement plans are published every year on REG website available at www.reg.rw/tenders/procurement-plans/
Related Projects
110kV Rulindo-Gabiro-Musha
This 110 KV line with its associated substations (Rulindo and Gabiro) connects Rulindo, Gabiro and Musha (Rwamagana) on a distance of 119km.
View projectImproving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP information published by Rwanda Energy Group.
View project110 kV Gishoma-Bugarama
This is a 13 km long 110 KV transmission line linking Gishoma Power plant to Bugarama Substation.
View projectImproving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP information published by Rwanda Energy Group.
View project220 kV Mirama-Shango
This is a 220 KV line connecting Rwanda to Uganda with a length of 93.5. It will facilitate the interconnection between the two countries.
View projectScaling- up energy access Project
(a) 25,438 households connected to national electricity, (b)179 schools, 29 health centers and 25 sector and cells administration offices with access to electricity in the project area, by (i) constructing 464Km of MV distribution lines and (ii) 710 Km of LV network.
View project