At a Glance
Households with off-grid access
July 2025
Households with on-grid access
July 2025
Total household electricity access
July 2025
National electricity access rate (grid + off-grid)
June 2026
Overview
Electricity access
As of end July 2025, the cumulative connectivity rate in Rwanda is 84.6% of Rwandan households including 59.6% connected to the national grid and 25.0% accessing through off-grid systems (mainly solar).
During the elaboration of the EDPRS II, the Government of Rwanda took a clear policy decision to diversify the sources of electricity from traditional dominant grid to include even off-grid connections. Subsequently, Households far away from the planned national grid coverage have been encouraged to use alternatively cheaper connections such as Mini-grids and Solar Photovoltaics (PVs) to reduce the cost of access to electricity whilst relieving constraints on historical government subsidies.
District | Access rate |
Bugesera | 81.9% |
Burera | 90.8% |
Gakenke | 97.2% |
Gasabo | 89.1% |
Gatsibo | 71.1% |
Gicumbi | 81.4% |
Gisagara | 63.4% |
Huye | 75.1% |
Kamonyi | 81.0% |
Karongi | 89.7% |
Kayonza | 79.0% |
Kicukiro | 92.1% |
Kirehe | 77.8% |
Muhanga | 98.0% |
Musanze | 79.5% |
Ngoma | 79.6% |
Ngororero | 95.3% |
Nyabihu | 79.6% |
Nyagatare | 76.1% |
Nyamagabe | 79.8% |
Nyamasheke | 97.4% |
Nyanza | 86.7% |
Nyarugenge | 91.3% |
Nyaruguru | 88.8% |
Rubavu | 82.6% |
Ruhango | 85.6% |
Rulindo | 85.7% |
Rusizi | 90.4% |
Rutsiro | 97.4% |
Rwamagana | 86.7% |
NATIONAL | 84.6% |
Explore this area
On-grid Access
As of July 2025, the cumulative connectivity rate in Rwanda is 84.6% of Rwandan households whereby 59.6% of all households in Rwanda are connected to the national grid. The number of on-grid connections has grown more than 12 times over the last 20 years.
ExploreOff-grid Access
As of end of July 2025, the Off-grid access rate is 25.0% of Rwandan households. During the elaboration of the EDPRS II, the Government of Rwanda took a clear policy decision to diversify the sources of electricity from traditional dominant grid to include even off-grid connections. Subsequently, Households far away from the planned national grid coverage…
ExploreNational Electrification Plan
REG publishes the National Electrification Plan revision concept note as an official electricity-access planning document.
ExploreAccess by District
Reporting period: July 2025
| Bugesera | 81.9% |
|---|---|
| Burera | 90.8% |
| Gakenke | 97.2% |
| Gasabo | 89.1% |
| Gatsibo | 71.1% |
| Gicumbi | 81.4% |
| Gisagara | 63.4% |
| Huye | 75.1% |
| Kamonyi | 81.0% |
| Karongi | 89.7% |
| Kayonza | 79.0% |
| Kicukiro | 92.1% |
| Kirehe | 77.8% |
| Muhanga | 98.0% |
| Musanze | 79.5% |
| Ngoma | 79.6% |
| Ngororero | 95.3% |
| Nyabihu | 79.6% |
| Nyagatare | 76.1% |
| Nyamagabe | 79.8% |
| Nyamasheke | 97.4% |
| Nyanza | 86.7% |
| Nyarugenge | 91.3% |
| Nyaruguru | 88.8% |
| Rubavu | 82.6% |
| Ruhango | 85.6% |
| Rulindo | 85.7% |
| Rusizi | 90.4% |
| Rutsiro | 97.4% |
| Rwamagana | 86.7% |
Related Projects
110 kV Nyabarongo 1 HPP-Kilinda
This is a line of 28 km linking Nyabarongo Hydropwer to Kilinda Substation. It was completed in 2014.
View projectIncreasing Access to Electricity to Some Areas in Rwanda
Grid extention by 194 km of Medium Voltage lines and 489 km of Low Voltage lines and 133 distribution transformers
View project110 kV Ntendezi–Bugarama
This project included the construction of a 17.5 km transmission line linking Ntendezi and Bugarama with the associated substations. This line transmission line will ensure power stability in the West of Rwanda and CIMERWA factory
View projectEASSDP- Electricity Access Scale up and sector wide Approach development project. CR N° 4651-RW
EASSDP- Electricity Access Scale up and sector wide Approach development project. CR N° 4651-RW information published by Rwanda Energy Group.
View projectRusumo Falls Hydro Power Project
The project is being developed under NELSAP umbrella for Rwanda, Burundi and Tanzania funded by the World Bank. Rusumo falls Hydropower Project is planned to generate 80 MW and the power output will be shared equally by three countries. The project consists of concrete dam with crest length of 150m,Headrace Tunnel of 460m and a surface power station with…
View projectElectricity Access ScaIe-Up Project Loan Agreement N°1293P”
Electricity Access ScaIe-Up Project Loan Agreement N°1293P” information published by Rwanda Energy Group.
View project