What We Do

Methane Gas

Methane Gas Resources is found in the Lake Kivu in the Eastern African Rift Zone. The lake contains high concentrations of naturally occurring methane gas (CH4) and carbon dioxide (CO2), with the highest concentrations at depths ranging from 270m to 500m at an area of around 2,400 sq.km.

Overview

Methane Gas in Rwanda

Methane Gas Resources is found in the Lake Kivu in the Eastern African Rift Zone. The lake contains high concentrations of naturally occurring methane gas (CH4) and carbon dioxide (CO2), with the highest concentrations at depths ranging from 270m to 500m at an area of around 2,400 sq.km.

The oxygenated upper layer of the lake from the surface to a depth of 60m supports the lake’s biology. The resource is equally shared between Rwanda and the Democratic Republic of Congo.

Until 2004, extraction of the gas was done on a small scale, with the extracted gas being used to run boilers at a brewery in Gisenyi. Since then, the Government of Rwanda has prioritized the production of electricity from this unique resource in order to address the growing electrical energy deficit.

Completed and Ongoing Methane-to-Power Projects

a) KivuWatt project, a subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.

c) Shema Power Lake Kivu Ltd, signed a 25-year power purchase agreement (PPA) with the Rwanda Energy Group (REG) for a 56 MW net power output from methane gas. The Power plant is located on Nyamyumba sector in Rubavu District. Currently the power plant is generating 37.5 MW and will soon reach its full capacity.  

Project List

Related Projects

Methane gas

KivuWatt Project Phase I

A subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.

View project

Peat

Hakan Quantum Power Project

YUMN Ltd. is developing an 80 MW peat fired power plant in South Akanyaru prospect in Gisagara District and the project is to be developed as Public Private Partnership (PPP). On Feb 10, 2016, Amendment and Restatement Deeds for Power Purchase Agreement, Concession Agreement and Government Guarantee have been signed. Since February 2017 the project is und…

View project

Medium Voltage

Kigali Ring II

Installation of reactive power compensators (capacitor banks) at MV side of the following substations,: Gikondo, Jabana and Birembo. Each substation with 4.5MVAr;

View project