Methane Gas in Rwanda
Methane Gas Resources is found in the Lake Kivu in the Eastern African Rift Zone. The lake contains high concentrations of naturally occurring methane gas (CH4) and carbon dioxide (CO2), with the highest concentrations at depths ranging from 270m to 500m at an area of around 2,400 sq.km.
The oxygenated upper layer of the lake from the surface to a depth of 60m supports the lake’s biology. The resource is equally shared between Rwanda and the Democratic Republic of Congo.
Until 2004, extraction of the gas was done on a small scale, with the extracted gas being used to run boilers at a brewery in Gisenyi. Since then, the Government of Rwanda has prioritized the production of electricity from this unique resource in order to address the growing electrical energy deficit.
Completed and Ongoing Methane-to-Power Projects
a) KivuWatt project, a subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.
c) Shema Power Lake Kivu Ltd, signed a 25-year power purchase agreement (PPA) with the Rwanda Energy Group (REG) for a 56 MW net power output from methane gas. The Power plant is located on Nyamyumba sector in Rubavu District. Currently the power plant is generating 37.5 MW and will soon reach its full capacity.
Project List
Related Projects
Rusumo Falls Hydro Power Project
The project is being developed under NELSAP umbrella for Rwanda, Burundi and Tanzania funded by the World Bank. Rusumo falls Hydropower Project is planned to generate 80 MW and the power output will be shared equally by three countries. The project consists of concrete dam with crest length of 150m,Headrace Tunnel of 460m and a surface power station with…
View projectElectricity Access ScaIe-Up Project Loan Agreement N°1293P”
Electricity Access ScaIe-Up Project Loan Agreement N°1293P” information published by Rwanda Energy Group.
View project110kV Jabana-Mt. Kigali-Gahanga and associated substations
The project consists of building a 27km long 110KV transmission line linking Jabana, Mont Kigali up to Gahanga Substation.
View projectRuzizi III
Rusizi III Hydropower (145MW) construction project is supported by the World Bank, EU, AfDB among others with an expected investment capital of $450 million and is expected to be completed by 2024. The project is being developed under CEPGL umbrella for Rwanda, Burundi and DRC. Rusizi III hydropower project planned to generate 147MW and the power output w…
View projectKigali Network Strenghening 2
Rehabilitation of MV underground cable within Kigali city Centre, construction of a 1.5km four circuit overhead line between Gikondo and KBC; replacement of MV underground cables from KBC to Christus. This Project is divided in 3 lots:
View project110 kV Gasogi-KSEZ
The project consists of building a 2.2km long 110KV transmission line linking Gasogi substation to Kigali Special Economic Zone
View project