As of end of July 2025, the Off-grid access rate is 25.0% of Rwandan households. During the elaboration of the EDPRS II, the Government of Rwanda took a clear policy decision to diversify the sources of electricity from traditional dominant grid to include even off-grid connections. Subsequently, Households far away from the planned national grid coverage have been encouraged to use alternatively cheaper connections such as Mini-grids and Solar Photovoltaics (PVs) to reduce the cost of access to electricity whilst relieving constraints on historical government subsidies.
District | Off-grid |
Bugesera | 27.2% |
Burera | 20.1% |
Gakenke | 47.6% |
Gasabo | 1.8% |
Gatsibo | 33.9% |
Gicumbi | 29.5% |
Gisagara | 19.2% |
Huye | 25.3% |
Kamonyi | 32.7% |
Karongi | 38.6% |
Kayonza | 32.9% |
Kicukiro | 1.2% |
Kirehe | 31.1% |
Muhanga | 35.5% |
Musanze | 11.0% |
Ngoma | 34.1% |
Ngororero | 41.5% |
Nyabihu | 21.6% |
Nyagatare | 30.3% |
Nyamagabe | 41.1% |
Nyamasheke | 21.3% |
Nyanza | 33.8% |
Nyarugenge | 0.7% |
Nyaruguru | 39.0% |
Rubavu | 6.7% |
Ruhango | 27.4% |
Rulindo | 38.0% |
Rusizi | 17.3% |
Rutsiro | 33.8% |
Rwamagana | 26.5% |
NATIONAL | 25.0% |
Project List
Access by District
Reporting period: July 2025
| Bugesera | 27.2% |
|---|---|
| Burera | 20.1% |
| Gakenke | 47.6% |
| Gasabo | 1.8% |
| Gatsibo | 33.9% |
| Gicumbi | 29.5% |
| Gisagara | 19.2% |
| Huye | 25.3% |
| Kamonyi | 32.7% |
| Karongi | 38.6% |
| Kayonza | 32.9% |
| Kicukiro | 1.2% |
| Kirehe | 31.1% |
| Muhanga | 35.5% |
| Musanze | 11.0% |
| Ngoma | 34.1% |
| Ngororero | 41.5% |
| Nyabihu | 21.6% |
| Nyagatare | 30.3% |
| Nyamagabe | 41.1% |
| Nyamasheke | 21.3% |
| Nyanza | 33.8% |
| Nyarugenge | 0.7% |
| Nyaruguru | 39.0% |
| Rubavu | 6.7% |
| Ruhango | 27.4% |
| Rulindo | 38.0% |
| Rusizi | 17.3% |
| Rutsiro | 33.8% |
| Rwamagana | 26.5% |
Related Projects
110kV Rulindo-Gabiro-Musha
This 110 KV line with its associated substations (Rulindo and Gabiro) connects Rulindo, Gabiro and Musha (Rwamagana) on a distance of 119km.
View projectImproving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP information published by Rwanda Energy Group.
View project110 kV Gishoma-Bugarama
This is a 13 km long 110 KV transmission line linking Gishoma Power plant to Bugarama Substation.
View projectImproving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP information published by Rwanda Energy Group.
View project220 kV Mirama-Shango
This is a 220 KV line connecting Rwanda to Uganda with a length of 93.5. It will facilitate the interconnection between the two countries.
View projectScaling- up energy access Project
(a) 25,438 households connected to national electricity, (b)179 schools, 29 health centers and 25 sector and cells administration offices with access to electricity in the project area, by (i) constructing 464Km of MV distribution lines and (ii) 710 Km of LV network.