What We Do

Distribution

During the fiscal year 2025-26 The distribution network expanded by 5,285.43 km during FY 2025/26, reaching 43,013.8 km by June 2026, up from 37,728.36 km a year earlier growth of 14%. The year's construction comprised 841.13 km of medium voltage and 4,444.3 km of low voltage line, bringing the network to 13,357.93 km MV and 29,655.87 km LV.

Overview

Below map shows current existing and ongoing electricity distribution lines (Medium Voltage lines) as well as ongoing site.

Official REG energy infrastructure

 

Related Projects

Peat

Gishoma 15 MW Peat to Power Project

Since 2010, the Government started development of the 15MW peat power plant in Gishoma, Rusizi District, to reduce electricity deficit which the country was facing and to coincide with a significant growth of electricity demand observed in the region as a result of the expansion of the local cement factory and country development.

View project

Transmission , Medium Voltage

Kigali Ring I

The project consists of construction of 27km of 110kV transmission line from Jabana to Gahanga via Mont Kigali, construction of 110/30/15kV, 40MVA substation at Mont Kigali, 110/15kV; 20MVA substation at Gahanga; addition of a second transformer at Birembo (20MVA)

View project

Transmission

220 kV Kigoma-Butare-Ngozi-Gitega

The project consists of construction of 62km long transmission line from Kigom, Butare, Ngozi and Gitega. This 220KV line will facilitate interconnection and exchange electricity between Rwanda and Burundi

View project

Generation , Hydropower

Nyabarongo II Multipurpose project

Nyabarongo II (43.5MW) is a multipurpose project expected to cater for water supply, irrigation as well as electrical power generation. The project is also envisaged to mitigate the perpetual flooding downstream of the Nyabarongo River that has proved to be hazardous in the recent years. The project is fully funded by the Government of Rwanda is expected…

View project

Transmission

220 kV Rusumo- Bugesera-Shango

The project consists of construction of a 119km long 220KV transmission line with its associate substations which will evacuate power from Rusumo Hydropower Plant (under construction) to Bugesera up to Shango

View project