Overview
Methane Gas in Rwanda
Methane Gas Resources is found in the Lake Kivu in the Eastern African Rift Zone. The lake contains high concentrations of naturally occurring methane gas (CH4) and carbon dioxide (CO2), with the highest concentrations at depths ranging from 270m to 500m at an area of around 2,400 sq.km.
The oxygenated upper layer of the lake from the surface to a depth of 60m supports the lake’s biology. The resource is equally shared between Rwanda and the Democratic Republic of Congo.
Until 2004, extraction of the gas was done on a small scale, with the extracted gas being used to run boilers at a brewery in Gisenyi. Since then, the Government of Rwanda has prioritized the production of electricity from this unique resource in order to address the growing electrical energy deficit.
Completed and Ongoing Methane-to-Power Projects
a) KivuWatt project, a subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.
c) Shema Power Lake Kivu Ltd, signed a 25-year power purchase agreement (PPA) with the Rwanda Energy Group (REG) for a 56 MW net power output from methane gas. The Power plant is located on Nyamyumba sector in Rubavu District. Currently the power plant is generating 37.5 MW and will soon reach its full capacity.
Project List
Related Projects
110 kV Gishoma-Bugarama
This is a 13 km long 110 KV transmission line linking Gishoma Power plant to Bugarama Substation.
View projectImproving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP information published by Rwanda Energy Group.
View project220 kV Mirama-Shango
This is a 220 KV line connecting Rwanda to Uganda with a length of 93.5. It will facilitate the interconnection between the two countries.
View projectScaling- up energy access Project
(a) 25,438 households connected to national electricity, (b)179 schools, 29 health centers and 25 sector and cells administration offices with access to electricity in the project area, by (i) constructing 464Km of MV distribution lines and (ii) 710 Km of LV network.
View project220 kV Shango-Rubavu-Bwishyura-Kibuye
This is a 220 KV transmission line linking Shango, Rubavu, Bwishyura and Kibuye on a distance of 180km.
View projectRural electrification Project in Burera and Nyagatare Districts
The project will extend the national grid by 221.4 km of MV lines and 393.15 km of LV lines. A total of 18761 new connections will be made in Burera and Nyagatare Districts
View project