Electricity Service Connection Request

 

 Do you want to register for Electricity connection? Please click here to register now

 

Connection Processes and Stipulated Timeframes

Connection Process Category

Service delivery

Timeframes

Cost

Industrial area

and Industries located in 1km from the National grid

Submission of Application

1 Day

Free of charge

Field Survey

2 Days

Material Issuance, Construction & Installation

11 days

Free of charge

Testing & Commissioning

1 Day

Free of charge

 

Maximum 15 days

 

Industries between 1 and 5,3km to the National grid

Submission of Application

1 Day

 

Field Survey & Quotation

2 Days

Payments

1 Day

20,000,000 Rwf

Material Issuance Construction & Installation

10 Days

 

Installation, Testing & commissioning

1 Day

 

 

Maximum 15 days

 

Industries falling beyond 5,3km to the National grid

Submission  of Application

1 Day

 

Field Survey & Quotation

2 Days

Payments

1 Day

20,000,000 Rwf, for 1 to 5,3 km and 20,500,000 Rwf per km beyond 5,3 km

Material Issuance Construction & Installation

10 Days

 

Installation, Testing & commissioning

1 Day

 

 

Maximum 15 days

 

 